Where do I enter the work schedule so that overtime is calculated correctly?

On this page

    Admins can configure the Annual Working Schedule on the Web interface to define expected working hours, which are required for overtime calculation.

    Roles: Admin | Interface: Web

    1. Click on the Settings (cogwheel icon) in the top-right corner.
    2. Select Schedules from the left sidebar.
       


       

    3. Create (3) or edit (4) an Annual Working Schedule by defining the expected working hours for each day of the year.
    4. Assign the relevant employees to the schedule. Overtime is calculated by comparing their recorded hours against these expected hours.

    Note: If no working schedule is assigned to an employee, their expected working time is set to 0, and all recorded hours may be treated as overtime depending on company configuration.